Program Milestones

Phase 1: Planning

EPA Grant Agreement Executed

Completed

Federal Solar for All grant agreement signed and activated

Target: Feb 2024Completed: Jan 2024

Coalition Formation Complete

Completed

All founding coalition members recruited and MOUs executed

Target: Mar 2024Completed: Mar 2024
Phase 2: Outreach

Contractor Procurement Complete

Completed

Pre-qualify and onboard minimum 3 licensed solar contractors

Target: Aug 2024Completed: Jun 2024
Phase 3: Installation

Quality Inspection Protocol

Completed

Establish and execute quality inspection for all installations

Target: Mar 2025Completed: Feb 2025
Phase 2: Outreach

Community Outreach -- 2,000 Households

Completed

Reach 2,000 eligible households through outreach campaigns

Target: Jun 2025Completed: May 2025
Phase 3: Installation

First 100 Installations

Completed

Complete solar installations for first 100 households

Target: Jun 2025Completed: Apr 2025

500 Household Installation Target

Completed

Reach 500 cumulative household installations

Target: Sep 2025Completed: Aug 2025
Phase 2: Outreach

Workforce Training -- First Cohort

Completed

Graduate first cohort of 24 solar installation trainees

Target: Dec 2025Completed: Nov 2025
Phase 3: Installation

2,000 Household Target

In Progress

Complete installations for all 2,000 target households

Target: Dec 2026
Phase 4: Reporting

Final EPA Impact Report

Upcoming

Submit comprehensive program impact report to EPA

Target: Mar 2027